It's me. I got an answer for the following question but it just looks wrong lol. It's a decimal.
In a factory, machine 1 produces 8-inch (in.) pliers at the rate of 60 units per hour (hr) and 6-in. pliers at the rate of 70 units/hr. Machine 2 produces 8-in. pliers at the rate of 40 units/hr and 6-in. pliers at the rate of 20 units/hr. It costs 50 dollars per hr to operate machine 1, and machine 2 costs 30 dollars per hr to operate. The production schedule requires that at least 240 units of 8-in. pliers and at least 140 units of 6-in. pliers be produced during each 10-hr day. Which combination of machines will cost the least money to operate?
This is what I got:
Let x be no. of units to produce in machine 1 and
Let y be no. of units to produce in machine 2
Objective Function: C=50x+30y
Constraints:
x ≥ 0
y ≥ 0
60x+40y ≥ 240
70x+20y ≥ 140
Then I found the intercepts, plotted the graph, and ended up with .5 and 5.15 as answers...that doesn't seem right. ._.
Any help is appreciated as always.
Regards,
Jason