A, B and C need a certain unique time to do a certain work. C needs 1 hours less than A to complete the work. Working together, they require 30 minutes to complete 50% of the job. The work also gets completed if A and B start working together and A leaves after 1 hour and B works for a further 3 hours. How much work does C do per hour?
(A)16.66%
(B)33.33%
(C)50%
(D)66.66%
My attempt:
Let the total work be 100 units.
Let the work done by A,B and C be a units/hour,b units/hour,c units/hour respectively.
Let the time taken by A alone to complete the work be t hours.
ATQ: \begin{align*} (a+b+c) \cdot \frac{1}{2} & =50 \tag{1}\\ (a+b) \cdot 1+b \cdot 3 & =100 \tag{2}\\ c \cdot (t-1)& =100 \tag{3}\\ at & =100 \tag{4} \end{align*} Please help me solve these equations. When I am solving it is getting cumbersome.
Also if someone tells us some other way of solving, that would be helpful as well. Thanks.