What I have understood is that:
In the first case:
A starts the work and A finishes the work.
In the second case:
B starts the work and B finishes the work.
Otherwise, the time taken to complete the work would have been same in both the cases.
What I have understood is that:
In the first case:
A starts the work and A finishes the work.
In the second case:
B starts the work and B finishes the work.
Otherwise, the time taken to complete the work would have been same in both the cases.
Hint:
Let the parts of the work completed in a day by $A,B,C$ be $a,b,c$
$100=9a+8b=9b+\dfrac{26a}3\iff a=3b$
$\implies9(3b)+8b=100\implies b=?,a=3b=?$
Again, $\dfrac{100}5=a+b+c\implies c=?$
Let's indicate with 100 the work to be done and with x,y,z the productivity for A,B,C.
We know that
$$9x+8y=100$$
$$\left(8+\frac23\right)x+9y=100$$
$$5(x+y+z)=10$$
From the above equations you can find x,y,z: $x=\frac{60}{7}$, $y=\frac{20}{7}$, $z=\frac{60}{7}$
Thus
$17\frac23$ days need for B and C to complete the work.