The question I am working on is as follows,
You are in charge of managing a $200,000$-acre forest. Of these $200,000$ acres, $80,000$ can only grow pine and $40,000$ can only grow aspen. The remaining $80,000$ acres can grow either pine or aspen, or a mixture of both. The Land Expectation Value (LEV) for pine stands in the forest is $90$ Dollars per ac, for aspen stands the LEV is $50$ Dollars per ac, and for mixed stands it is $70$ Dollars per ac. You have three critical species in the forest, American Marten, Broadwing Hawk, and Three-toed Woodpecker. Your habitat conservation plan requires you to maintain habitat for $500$ American Marten breeding pairs, $600$ Broadwing Hawk breeding pair, and $450$ Three-toed Woodpecker breeding pairs. American Marten is found only on the pine and mixed forest types at an average density of $5$ breeding pairs per $1,000$ acres in pine and $2$ breeding pairs per $1,000$ acres in mixed forest. Broadwing Hawk is found at average densities of $1$ breeding pair per $1,000$ acres of pine, $3$ breeding pairs per $1,000$ acres in mixed forest, and $6$ breeding pairs per $1,000$ acres in aspen. Three-toed Woodpeckers are found at average densities of $2$ breeding pairs per $1,000$ acres of pine, $4$ breeding pairs per $1,000$ acres in mixed forest, and $1$ breeding pair per $1,000$ acres in aspen. In addition to meeting these three habitat goals, you would like to maximize the LEV of the forest.
I am having trouble with a certain part of the problem. It states that you can have a $200,000$ acre forest that has $80,000$ dedicated to pine and $40,000$ dedicated to aspen. There is the remaining $80,000$ that can be mixed or either pine or Aspen. I have written the $z$ function like this,
Link to all the data from problem organized for ease
$$Max(Z) = P(\text{acres pine}) * 90 + A(\text{acres aspen}) * 50 + M(\text{acres mixed}) * 70$$
with constraints that I have written so far,
$$0.005*P + 0.002*A + 0*M = 500$$ (marten)
$$0.001*P + 0.003*A + 0.006*M = 600$$ (Hawk)
$$0.002*P + 0.003*A + .001*M = 450$$ (WoodPecker)
$$P >= 80,000$$
$$A >= 40,000$$
$$P >= 0$$
$$A >= 0$$
$$M >= 0$$
Where I'm getting confused is with the remaining $80,000$ acres that can be mixed, pine, or aspen. I don't know how to write it out so $M$ is either $0$ or $80,000$. I may be approaching this problem incorrectly, I'm just learning how to do linear programming. Any help would be greatly appreciated.